Guideline of HSE Critical Equipment Management Practices Survey

Objective of the Survey
Gather the regional practices pertaining the HSE Critical equipment classification basis and processes, stewardship, deferral and relevant performance statistics.

Nomenclature

 

Asset An asset is an engineered piece of equipment.
HSECES Health Safety Environment Critical Equipment & Systems. The failure of which could cause or contribute substantially to; or purpose of which is to prevent or control the effects of a Major Accident Hazard (MAH) scenario as defined from COMAH study
COMAH A safety study to demonstrate that they have taken all measures necessary to prevent major accidents and to limit the consequences to people and the environment of any that do occur. Example Pressure Safety Valve, Safety Intrumentated System, Deluge System etc
Not Applicable (N/A) Not applicable. For those suvey responder to Indicate that the company has no applicable requirement/ system related to those described in the survey questions

Methodology of the Survey

  1. This survey is aiming to collect responses from all GPCA Member Companies (and Potential company from other regions)
  2. One collective response from each company will be accepted. This should be a collective result from Process Safety/ Asset Integrity, HSE, Maintenance, Operation, Project, Inspection functions/departments
  3. The focal point of each company will enter the collective response into the automated survey tool onthe GPCA portal. Provide further comment/ justifications for the respective survey question

Survey Questionnaire for HSE Critical Equipment Management Practices

HSECES Identification

1. The department that is responsible for the process of HSECES Management is independent from operation, maintenance, technical and project team. The HSECES Management includes
- Identification of HSECES,
- the development and alignment of integrity assurance tasks with routine Preventive Maintenance & Inspection,
- Deferral Processes in Managing the Integrity of HSECES
- Performance Monitoring
- Integrity Audit and Assurance

Response:

Remarks:


2. Is the percentage of HSECES from the total asset is more than 50%? What is the percentage HSECES from the total assets? Specify the percentage in the remark column provided. Note: The purpose of this data is only for reference

Response:

Remarks:


3. Is a risk based selection criteria exists that qualifies an asset as HSECES?

Response:

Remarks:


4. Is HSECES list updated periodically based on the requirement of local applicable regulation or based on international standards e.g. COMAH/ HSE Impact Assessment Revalidation

Response:

Remarks:


5. Is the bowtie analysis used as part of the HSECES identification process

Response:

Remarks:


6. Is the asset list (equipment list) available in the CMMS (computerized maintenance management system e.g. SAP/ MAXIMO, etc.) with clear identification code for HSECES?

Response:

Remarks:


7. Does the HSECES tag list prepared for new/ modification projects and is uploaded to CMMS prior to commissioning of the facility

Response:

Remarks:


8. Does HSECES identification process at tag level include the reviews of process safety documents such as PFD, P&IDs, layouts, engineering deliverables, HSE studies, etc.

Response:

Remarks:


9. Does a document exist as part of the project deliverable that provides the details and justifications of an HSECES

Response:

Remarks:


10. Do the discipline focal points (site/ project) validate the HSECES locations/ tags list to ensure correctness and consistency

Response:

Remarks:


11. Does company HSECES focal point (e.g. asset integrity/ process safety engineer) review the HSECES tag list and ensured consistency with the company HSECES identification procedure

Response:

Remarks:


Maintaining the Integrity of HSECES

12. Does the maintenance, inspection and testing requirements for all the identified HSECES are ensured that are aligned with the recommendation from manufacturer and/or industrial standards. These requirements are made available in the CMMS (computerized maintenance management system e.g. SAP/ MAXIMO, etc.)

Response:

Remarks:


13. Does amendment of HSECES maintenance, inspection and testing requirements meet the requirements and comply with MOC requirement process.

Response:

Remarks:


14. Is the training gaps and development plan required to handle HSECES maintenance, inspection and testing requirement identified for direct hired employee and contractor.

Response:

Remarks:


Deferral Processes in Managing the Integrity of HSECES

15. Is a clearly defined process for managing failures and deviation from HSECES maintenance, inspection and testing requirements is in place.

Response:

Remarks:


16. Does a clearly defined process for managing deferral of HSECES from the scheduled preventive maintenance task is in place

Response:

Remarks:


17. Does the HSECES deferral process involves risk identification, evaluation and specifying the relevant mitigation controls. Different risk level of the HSECES deferral required different level of management approval

Response:

Remarks:


18. Does the deferral process permit an equipment to be deferred if the historical inspection records are satisfactory and risk assessed

Response:

Remarks:


19. Does the triggering of deferral process have a grace period for example 30days from the due date of the preventive maintenance task.

Response:

Remarks:


20. Does the HSECES deviation mitigating processes triggers the equipment failure investigation process for identifying the root cause and actions to avoid the recurrence.

Response:

Remarks:


21. Is a cumulative risk re-evaluation process is in place to periodically review the risk profile of the unit/plant with respect to the total number of the unresolved HSECES deferral / deviations and open remedial actions.

Response:

Remarks:


Performance Monitoring

22. Are formal processes for the identification, monitoring, measuring and trending the performance of HSECES Integrity are in place

Response:

Remarks:


23. Are the identified performance indicators are tracked against the performance targets to demonstrate compliance and reported to management

Response:

Remarks:


24. Is on time execution of HSECES preventive maintenance task is one of the measurement to monitor the performance of HSECES management

Response:

Remarks:


25. Is a percentage of HSECES preventive maintenance work order past the maintenance, inspection and testing requirements is one of the measurements to monitor the performance of HSECES management

Response:

Remarks:


26. Is there a process to track, investigate and improve the failure of HSECES bad actors

Response:

Remarks:


Audit and Assurance

27. Is an Audit and Assurance are performed by an independent body during the key asset life cycle i.e. FEED, EPC, Decommissioning and Operating Phases to confirm whether the HSECESs are designed, constructed, installed, commissioned, maintained, decommissioned and abandoned as per the requirements of the identified integrity assurance tasks

Response:

Remarks:


28. Is there a pre-defined timeline in each of the project stages to carry out the Audit and Assurance requirement

Response:

Remarks:


29. Is a Corrective Action Workshop conducted post the Audit and Assurance to align the finding and actions to close the gaps

Response:

Remarks:


30. Is the agreed actions entered into an action tracking register and closed effectively

Response:

Remarks:


31. Is there a procedure that defines the identification process of HSECES? Please share your company definition for EHS critical equipment and system in the remarks column.

Remarks:


SUPPORTING DOCUMENTS

Files should be in JPEG, JPG, PNG or PDF format only